Q1. Material at site Account is a _____________ साइट पर सामग्री खाता एक _____________ है
- A) Purchase head
- B) Register of works
- C) Suspense head
- D) Material head
Correct Answer: Suspense head
Explanation: Explanation :
Q2. e-RA Electronic Reverse Auction shall be the preferred method for Works and Services for Tenders valued more than ________ & ________ in each case respectively ई-आरए इलेक्ट्रॉनिक रिवर्स नीलामी प्रत्येक मामले में क्रमशः ________ और ________ से अधिक मूल्य की निविदाओं के लिए कार्यों और सेवाओं के लिए पसंदीदा तरीका होगा।
- A) Rs. 10 Crores & Rs. 50 Crores
- B) Rs. 50 Crores & Rs. 10 Crores
- C) Rs. 10 Crores & Rs. 10 Crores
- D) Rs. 50 Crores & Rs. 50 Crores
Correct Answer: Rs. 50 Crores & Rs. 50 Crores
Explanation: Explanation :
Q3. Material at site Account is a _______ साइट पर सामग्री खाता एक _______ है
- A) Purchase head
- B) Register of works
- C) Suspense head
- D) Material head
Correct Answer: Suspense head
Explanation: Explanation : 1. Source: 1436 Engineering Code 2. It is one of the Suspense heads operated on erstwhile Demand No. 16. 3. M A S A/c records the stores obtained for specific works. 4. Material obtained for specific works should be kept outside the accounts of any other category of stores. Such material, be deemed to be “Material At Site”. 5. MAS A/c – To be maintained for works valuing Rs. One lakh and for Track Renewal works valuing Rs. 3 Lakhs. 6. Maintained by the Executive in charge of the work. Custody of Materials under MAS – either under the custody of the in charge of Work or kept in Engineering Stores Depot under the custody of DMS/DSK
Q4. In Model SOP (Schedule of Powers), Part B covered about ______ मॉडल एसओपी (शक्तियों की अनुसूची) में, भाग बी में ______ के बारे में बताया गया है
- A) Commercial
- B) Establishment
- C) Medical
- D) Works
Correct Answer: Medical
Explanation: Explanation : Parts of MSOP
Q5. Project worth of Rs. 800 Crores requires approval of __________________ परियोजना का मूल्य रु. 800 करोड़ के लिए __________________ की मंजूरी की आवश्यकता है
- A) Chairman & CEO, Railway Board
- B) EBR - Expanded Board for Railways
- C) CCEA - Cabinet Committee on Economic Affairs
- D) Minister of Railways
Correct Answer: Minister of Railways
Explanation: Explanation : 1. Projects costing Rs. 50 Crores and above - Preparation of DPR - Detailed Project Report is mandatory before they are processed for sanction of the competent authority.
Q6. e-RA - Electronic Reverse Auction for Works Tenders is ___________ ई-आरए - कार्य निविदाओं के लिए इलेक्ट्रॉनिक रिवर्स नीलामी ___________ है
- A) Mandatory, irrespective of value
- B) Mandatory for Tenders above Rs. 10 Crore
- C) Optional
- D) None of these
Correct Answer: Optional
Explanation: Explanation : Source: Railway Board Letter No. 2018/CE-I/CT/18 dated 21.11.2024 If local conditions allow, Railways may decide to adopt e-RA on case to case basis, with no further negotiation with L1 if L1 is selected through e-RA process
Q7. Which one of the following option cannot be taken as material modifications on lines under construction and open line works estimated to cost rupees one Crore and over? (Appendix3 Exam Model Paper 1) निम्नलिखित में से कौन सा विकल्प निर्माणाधीन लाइनों और खुली लाइन कार्यों पर सामग्री संशोधनों के रूप में नहीं लिया जा सकता है, जिनकी अनुमानित लागत एक करोड़ रुपये और उससे अधिक है? (परिशिष्ट 3 परीक्षा मॉडल पेपर 1)
- A) Any change in the alignment likely to affect the facilities offered to the public in the neighborhood or likely to increase or decrease the length of the line by 100 meters.
- B) Any alteration in the type or number of engines or vehicles provided in an estimate for rolling stock.
- C) Introduction of any new station or omission of any station.
- D) None of the above
Correct Answer: None of the above
Explanation: Explanation : Authority: ACS 59 dated 26.09.2022 (to the Engineering Code 2012) and Paras 1109 to 1112 of Engineering Code 2012 नोट:
Q8. As 'cash' forms, on an average about ___________ of the total expenditure of a Railway, Exchequer Control has the merit of providing an effective means of monitoring a substantial part of the expenditure on a day-to-day basis. चूंकि, रेलवे के कुल व्यय का औसतन लगभग ___________ 'नकद' होता है, राजकोष नियंत्रण में दिन-प्रतिदिन के आधार पर व्यय के एक बड़े हिस्से की निगरानी का एक प्रभावी साधन प्रदान करने की योग्यता होती है।
- A) 30 %
- B) 90 %
- C) 70 %
- D) 50 %
Correct Answer: 70 %
Explanation: Explanation : Budgetary Control – Covers Cash and Adjustments. Part of Ways and Means
Q9. In case the contractor fails to submit the requisite PG even after ______ from the date of issue of LOA, the Service contract shall be terminated duly forfeiting EMD and other dues, if any payable against that contract. यदि ठेकेदार एलओए जारी होने की तारीख से ______ के बाद भी अपेक्षित पीजी जमा करने में विफल रहता है, तो ईएमडी और अन्य देय राशि, यदि उस अनुबंध के विरुद्ध देय हो, को जब्त करते हुए सेवा अनुबंध को समाप्त कर दिया जाएगा।
- A) 30 days
- B) 45 days
- C) 60 days
- D) 90 days
Correct Answer: 90 days
Explanation: Explanation : PG - Performance Guarantee: A. 5% of the Contract Value B. 4 separate parts i.e., each 1.25 % of the Contract Value C. Due period: 30 days from the LOA D. 60 days - If the Contractor fails to furnish after 60 days from the LOA, a notice will be served to the Contractor to pay the same within 90 days from LOA E. 60th day is Bank Holiday or office closure, the next working should be considered as the last day for submission of PG . F. 15% - Penal Interest - 31st day to the Day of submitting PG The consequences of failure to submission of PG within 90 days are:
Q10. The work of highly technical in nature in which accuaracy is more important than cost of the work - What is the type of Tender system is preferred ? उच्च तकनीकी प्रकृति का कार्य जिसमें सटीकता कार्य की लागत से अधिक महत्वपूर्ण है - किस प्रकार की निविदा प्रणाली को प्राथमिकता दी जाती है?
- A) Open Tender
- B) Limited Tender
- C) Global Tender
- D) Two-Packet Tender System
Correct Answer: Two-Packet Tender System
Explanation: Explanation : (clause 7 A of GCC - General Conditions of Contract ) Main Object